Commissioning and Fault Finding
Part No. 057-120 8660 OPERATING MANUAL ISSUE 1 07/05/2010 ADM
68
8 COMMISSIONING
8.1.1 PRE-COMMISSIONING
Before the system is started, it is recommended that the following checks are made:-
1. The unit is adequately cooled and all the wiring to the module is of a standard and rating compatible with the
system.
2. Check all mechanical parts are fitted correctly and that all electrical connections (including earths) are
sound.The unit DC supply is fused and connected to the battery and that it is of the correct polarity.
3. Check the operation of the MSC datalink. Use the DSE Config Suite to check this on the SCADA | BUS | MSC
LINK page. Verify the number of sets on the bus.
4. Ensure all 8610 controllers in the system have been fully commissioned using the DSE “Four Steps to
Successful Synchronising”.
5. Place the 8660 module into STOP mode. Place the 8610(s) into AUTO mode. Initiate a start by pressing the
START button of the 8660. All 8610’s start upon receipt of the MSC start command.
6. The bus will remain off load so long as the mains supply is healthy and on load.
7. Press the 8610 STOP button to remove the start request and stop the set(s).
8. Set the modules internal clock/calendar to ensure correct operation of the scheduler and event logging
functions. For details of this procedure see section entitled Front Panel Configuration – Editing the date and
time.
9. If, despite repeated checking of the connections between the 8600 series controller and the customer’s
system, satisfactory operation cannot be achieved, then the customer is requested to contact the factory for
further advice on:-